We collect cookies to analyze our website traffic and performance; we never collect any personal data.Cookies Policy
Accept
Michigan Post
Search
  • Home
  • Trending
  • Michigan
  • World
  • Politics
  • Top Story
  • Business
    • Business
    • Economics
    • Real Estate
    • Startups
    • Autos
    • Crypto & Web 3
  • Tech
  • Lifestyle
    • Lifestyle
    • Food
    • Beauty
    • Art & Books
  • Health
  • Sports
  • Entertainment
  • Education
Reading: Thames crossing delayed after planning it price greater than world’s longest street tunnel
Share
Font ResizerAa
Michigan PostMichigan Post
Search
  • Home
  • Trending
  • Michigan
  • World
  • Politics
  • Top Story
  • Business
    • Business
    • Economics
    • Real Estate
    • Startups
    • Autos
    • Crypto & Web 3
  • Tech
  • Lifestyle
    • Lifestyle
    • Food
    • Beauty
    • Art & Books
  • Health
  • Sports
  • Entertainment
  • Education
© 2024 | The Michigan Post | All Rights Reserved.
Michigan Post > Blog > Politics > Thames crossing delayed after planning it price greater than world’s longest street tunnel
Politics

Thames crossing delayed after planning it price greater than world’s longest street tunnel

By Editorial Board Published October 9, 2024 7 Min Read
Share
Thames crossing delayed after planning it price greater than world’s longest street tunnel

The destiny of Britain’s greatest street scheme hangs within the steadiness after ministers delayed giving it the go forward – regardless of over £800m being spent on it so far.

The federal government mentioned it wanted extra time to think about whether or not to grant a growth order for The Decrease Thames Crossing (LTC), together with reviewing its price.

The 14 mile venture was first proposed in 2009, and would join Kent and Essex by way of a street and tunnel beneath the River Thames to scale back congestion.

Politics Dwell: Sunak makes ‘fireplace and rehire’ jibe over Sue Grey’s exit

Nationwide Highways revealed in a Freedom of Info (FoI) request earlier this 12 months that £295m has been spent on the applying course of for the LTC. General spending, together with technical surveys and land buying prices, has surpassed £800m – all earlier than a spade has hit the bottom.

As identified by pro-growth marketing campaign group Britain Remade, the planning payment alone is greater than twice the associated fee it took Norway to truly construct the longest street tunnel on the earth.

The Laerdal tunnel, connecting Oslo and Bergen, solely price £140m, adjusted for inflation, the thinktank’s head of coverage Sam Dumitriu mentioned.

“This is the most scrutinised planning application in history and yet still we can’t get a decision on whether the project should get permission.”

Picture:
A view of the River Thames from Gravesend, on the proposed Decrease Thames Crossing. Pic: PA

Planning software ‘5 occasions lengthy because the street itself’

Britain Remade has beforehand revealed how Nationwide Highways has needed to produce 359,866 pages throughout 2,383 separate paperwork within the software course of, together with redrafts and resubmissions.

Laid finish to finish it might stretch 66 miles, nearly 5 occasions so long as the street itself.

Mr Dumitriu mentioned the most recent setback “speaks to a wider problem with our planning system”.

He mentioned: “Projects go through enormous hurdles, every single I dotted, T crossed, countless environmental studies, analyses, surveys, 360,000 pages overall and yet still even after all of that work and money spent, projects can still get delayed because a minister has decided to kick it into the long grass.”

The preliminary deadline for a choice on whether or not to grant a growth consent order enabling Nationwide Highways to construct the street was scheduled for 20 June, however was delayed due to the overall election.

Transport Secretary Louise Haigh was then on account of signal it off by final Friday, after receiving the planning inspectors’ suggestion three months in the past.

Please use Chrome browser for a extra accessible video participant

Prime Minister Keir Starmer and former Prime Minister Rishi Sunak attend the State Opening of Parliament.
Pic Reuters

1:50

‘Financial development a basic mission’

However in a written assertion to parliament this week, she mentioned it was “necessary” to increase the deadline for a choice to Could subsequent 12 months to provide the brand new authorities extra time for the applying to be thought-about.

She mentioned that included “any decisions made as part of the spending review” .

The cupboard minister later instructed LBC that she needed to “have confidence that the funding will be made available”, and that she believed the general prices of the venture have hit £1bn.

She mentioned that determine was “shocking” and her authorities desires to “radically change the way our planning and infrastructure works”.

Govt beneath strain over development guarantees

Labour is beneath strain to “get Britain building” – this being a central plank of their manifesto pledge to develop the economic system.

However Chancellor Rachel Reeves is anticipated to axe or delay infrastructure tasks in her Autumn Funds as a part of efforts to fill a £22bn “black hole” within the economic system.

Spreaker

This content material is offered by Spreaker, which can be utilizing cookies and different applied sciences.
To indicate you this content material, we want your permission to make use of cookies.
You should use the buttons beneath to amend your preferences to allow Spreaker cookies or to permit these cookies simply as soon as.
You may change your settings at any time by way of the Privateness Choices.

Sadly we’ve been unable to confirm when you’ve got consented to Spreaker cookies.
To view this content material you should utilize the button beneath to permit Spreaker cookies for this session solely.

Allow Cookies
Enable Cookies As soon as

👉 Faucet right here to observe Politics at Jack and Sam’s wherever you get your podcasts 👈

Learn Extra:Labour lead over Tories falls to only one level – pollHow fiscal guidelines are impeding long-term investments

If authorized, the LTC is anticipated to price £9bn and take six years to construct – however delays might make that much more costly on account of price pressures like inflation, Mr Dumitriu mentioned.

Whereas it’s a complicated venture, analysis from Britain Remade has discovered we’re spending as much as eight occasions extra on rail and street tasks than our European neighbours due to mountains of crimson tape and “nimby opposition”.

Thurrock Council in Essex has persistently opposed the LTC, citing damaging financial, social and environmental impacts, although the chief of Kent’s Dartford Borough Council is in favour of the scheme.

Native campaigners Thames Crossing Motion Group claims the crossing can be “hugely destructive and harmful”, and a waste of cash.

Nationwide Highways says the LTC is required to ease congestion on the notoriously busy Dartford Crossing, which in itself is costing the UK economic system £200m a 12 months in sitting visitors, and that the scheme would double street capability throughout the Thames east of London.

TAGGED:costcrossingdelayedlongestplanningroadThamestunnelworlds
Share This Article
Facebook Twitter Email Copy Link Print

HOT NEWS

Latest Laker Deandre Ayton is able to show the doubters incorrect

Latest Laker Deandre Ayton is able to show the doubters incorrect

Sports
July 9, 2025
Heatwave possible killed 263 individuals in London, research estimates

Heatwave possible killed 263 individuals in London, research estimates

An additional 263 Londoners possible died within the current heatwave, based on stark new estimates.It…

July 9, 2025
Ambulance rides save lives

Ambulance rides save lives

LANSING, Mich. (WLNS) — One cough, a copious quantity of phlegm and blood, and immediately…

July 9, 2025
Dodgers battle towards the Brewers, prolong dropping streak to 5 video games

Dodgers battle towards the Brewers, prolong dropping streak to 5 video games

MILWAUKEE — The sport plan, supervisor Dave Roberts mentioned Tuesday afternoon, was easy.Because the Dodgers ready to…

July 9, 2025
Greater than 110 injured after Marseille wildfire, minister says

Greater than 110 injured after Marseille wildfire, minister says

Greater than 110 individuals have been injured after wildfires broke out in Marseille, France's inside…

July 9, 2025

YOU MAY ALSO LIKE

Can PM flip diplomatic work with Macron into concrete motion on migration?

Emmanuel Macron addressing parliament within the Palace of Westminster's Royal Gallery was a extremely anticipated second within the lengthy historical…

Politics
July 8, 2025

Norman Tebbit: Thatcher’s true believer was a bruiser till the very finish

Norman Tebbit was one in every of Margaret Thatcher's true believers and one in every of her most loyal allies.In…

Politics
July 8, 2025

UN criticises Starmer’s welfare reforms and warns measures will ‘enhance poverty charges’

A UN committee on incapacity rights has criticised the UK authorities's welfare reforms, saying they may "increase poverty rates". In an…

Politics
July 8, 2025

UK and France have ‘shared accountability’ to sort out unlawful migration, Emmanuel Macron says

Emmanuel Macron has stated the UK and France have a "shared responsibility" to sort out the "burden" of unlawful migration,…

Politics
July 8, 2025

Welcome to Michigan Post, an esteemed publication of the Enspirers News Group. As a beacon of excellence in journalism, Michigan Post is committed to delivering unfiltered and comprehensive news coverage on World News, Politics, Business, Tech, and beyond.

Company

  • About Us
  • Newsroom Policies & Standards
  • Diversity & Inclusion
  • Careers
  • Media & Community Relations
  • Accessibility Statement

Contact Us

  • Contact Us
  • Contact Customer Care
  • Advertise
  • Licensing & Syndication
  • Request a Correction
  • Contact the Newsroom
  • Send a News Tip
  • Report a Vulnerability

Term of Use

  • Digital Products Terms of Sale
  • Terms of Service
  • Privacy Policy
  • Cookie Settings
  • Submissions & Discussion Policy
  • RSS Terms of Service
  • Ad Choices

© 2024 | The Michigan Post | All Rights Reserved

Welcome Back!

Sign in to your account

Lost your password?